Al-Taj News – The World Bank disbursed $361.13 million out of $500 million allocated for the Electricity Sector Efficiency and Supply Reliability Program in Jordan, while cost savings and additional revenues for the National Electric Power Company rose to 188.39 million dinars.
According to a World Bank report, the financing disbursement rate reached about 72.2%, while the program maintained a “satisfactory” rating in terms of progress made toward achieving its developmental objectives, overall implementation level, and progress in electricity sector efficiency, despite challenges related to financial sustainability.
The program’s financing is distributed across two loans worth $250 million each; the World Bank approved the first in March 2023, while it approved the additional financing in April 2025. The bank disbursed the full value of the first loan, in addition to $111.13 million of the additional financing, at a disbursement rate of 44.45%, while the value of undisbursed financing reaches about $138.88 million.
The implementation of the program continues until the end of February 2028, and aims to improve electricity sector efficiency, reduce costs, increase revenues, and maintain the reliability of electricity supply and renewable energy supplies, alongside enhancing the governance of the National Electric Power Company and managing financial risks in the sector.
The report showed an increase in cost savings and additional revenues for the National Electric Power Company by 17.8%, reaching 188.39 million dinars in the September reading, compared with 159.92 million dinars in last April’s reading, an increase of 28.47 million dinars.
The World Bank indicated that adjusting the bulk supply tariff for the National Electric Power Company contributed to achieving savings worth 16.9 million dinars during the second half of 2025, alongside the company continuing to receive mining royalties due from the Attarat project on a monthly basis.